Week 04: Concrete Mixer Delivery and Borehole Drilling
A concrete mixer was delivered to the site for pouring the German floor casting. The foundation was laid and work on both the interior and exterior block walls commenced. Due to the ongoing scarcity of water on the project, a borehole (well) was put in place. This ensured the availability of water resources required for the concrete pours. While initially planned for a different phase, the borehole was drilled ahead of schedule, alleviating the stress of searching for water each day.