Scaffolding
Second floor
Lintel work
Concrete mixer delivered for German floor casting. Block walls erected. Borehole drilled early due to water shortage, aiding concrete work.
2nd floor work
Second floor slab work
Interior work
The footers were backfilled in preparation for the installation of the German floor casting (slab). It then tampered down using a plate tamper.
No construction updates
No construction
Laying exterior block wall and framing window openings
Water scarcity posed initial challenges during footer foundation construction, resolved through innovative solutions like water tanks and manual concrete mixing.