top of page

Orphanage Updates Archive

Filter by Months
Week 04: Concrete Mixer Delivery and Borehole Drilling

Week 04

Week 04: Concrete Mixer Delivery and Borehole Drilling

Concrete mixer delivered for German floor casting. Block walls erected. Borehole drilled early due to water shortage, aiding concrete work.

Week 01: Foundation Construction

Week 01

Week 01: Foundation Construction

The construction site was prepared by clearing and leveling, providing a clean slate for the foundation work. Rebar installation for the foundation columns followed, ensuring a robust and stable base for the construction project.

Week 03: Backfilling and Compaction of Footers

Week 03

Week 03: Backfilling and Compaction of Footers

The footers were backfilled in preparation for the installation of the German floor casting (slab). It then tampered down using a plate tamper.

Week 02: Dealing with Water Challenges

Week 02

Week 02: Dealing with Water Challenges

Water scarcity posed initial challenges during footer foundation construction, resolved through innovative solutions like water tanks and manual concrete mixing.

bottom of page